Unknowns Under the Floor: What ENR's Midwest Project Profiles Teach About Existing-Conditions Risk, and Why the Headline Stories Need Checking

David Miller•Nov 27, 2026•
6 min read
Share
SIGN UP AND GET
10% OFF
Sign up for our newsletter and get 10% off your next purchase!
By subscribing, I agree to LearnFormula's email marketing. I can unsubscribe anytime. See Privacy Policy.

ENR's latest coverage is headlined around a Texas authorization for a power plant serving an AI campus, along with stories on a Jacobs modification job at DFW Skylink, a Purdue University small reactor test facility, and a Michigan order halting Enbridge Line 5 tunnel permitting. The problem for working engineers is that the pages behind those headlines do not contain the reporting. The text captured from the primary article and from the three supporting pages, including the DFW Skylink item, the Purdue item and the Line 5 item, is a set of 2025 Midwest Best Projects award profiles. None of them describes a Texas plant, a terminal contract, a reactor test program or a permitting halt.

That gap matters for how this story gets used. Until the underlying reporting is checked, the headline claims should not be passed along as fact. What the profiles do offer is a useful read on how award-winning Midwest projects handled risk, and that is the material worth working from this week.

What the Award Profiles Actually Describe

The clearest example is Catalyst Omaha, a Midwest Best Projects 2025 Award of Merit winner. The project is an adaptive reuse of the historic Omaha Steel Works site, established in 1906, where the team combined two vacant buildings into one 170,000-square-foot, three-story facility. The listed team includes Koelbel & Co. as owner, GreenSlate Development and the University of Nebraska Medical Center as owner/developer, Alley Poyner Macchietto Architecture as lead designer, Boyd Jones as general contractor, Olsson as civil engineer, TD2 as structural engineer and Morrissey Engineering as MEP engineer.

The profile is candid about what went wrong on paper. Soft subgrades and the absence of as-built drawings meant the team could not rely on existing documents. As the write-up puts it,

“Given the site’s history, unknowns were inevitable.”
The response was to combine building scans with detailed hand measurements, which gave the team a working picture of conditions before it committed to a sequence.

Once demolition exposed the structure, the crew installed temporary bracing and cabling to keep the frame stable. The team removed and rebuilt several walls and found an additional 8 inches of existing flooring that was not in the record. Vibration monitoring during soil compaction protected the remaining structure, including the original brick, and old steel columns were reinforced rather than replaced.

Other Projects Show the Same Pattern

The Fields Studios in Chicago, another Award of Merit winner, faced a similar problem on a 23-acre former rail site. Old foundations and embedded rails required geotechnical engineers to decide whether structures should stay in place or come out. Procurement was a separate constraint: some key mechanical and electrical components had lead times exceeding a year, and the team engaged local builders to deliver those components within 40 weeks.

The L3Harris Payload Manufacturing and Integration Facility in Fort Wayne, Indiana, faced a different constraint. Renovating an operating, highly secure facility meant phasing the work and staging outages and system transitions to the minute to protect sensitive lab operations. The team used 3D modeling to coordinate dense systems and catch clashes before field installation, and the contractor added specialized cleaning protocols to protect air quality where new construction met active labs.

The Anna Scripps Whitcomb Conservatory in Detroit adds one more example. The 120-year-old glasshouse had limited as-built documentation, and access to its dome for inspection was initially not possible. The team built a cantilevered scaffolding system around the structure, tied it into interior scaffolding and sequenced the upper window removal and replacement carefully.

Key Takeaway: In every profile, the schedule and budget risk came from information that was missing or uncertain before work started, such as drawings, subgrades, buried rails or inaccessible structure. The teams that handled it best measured conditions directly and built inspection and monitoring into the sequence.

What This Means for Engineering Teams

For practitioners, the practical lesson is to treat existing conditions as a design input rather than a field surprise. Where as-built drawings are absent, the profiles suggest pairing scanning with hand verification, and budgeting time for temporary works such as bracing and monitoring. Where a project will run for more than a year on long-lead equipment, the Fields Studios example shows that procurement strategy needs to be settled early, not after the first delay.

Phased work in occupied or secure facilities also needs its outage plan written before mobilization. The L3Harris profile shows that tight coordination between 3D models and field crews can catch conflicts early, which is worth requesting on comparable jobs.

What to Watch Next

The immediate task is verification. Before citing the Texas power plant authorization, the DFW Skylink modification, the Purdue reactor test program or the Line 5 permitting halt, check the original filings, agency notices or company releases. If those confirm the headlines, the details, including dollar values, capacities and schedules, should be pulled from those primary documents rather than from this set of pages. If the reporting does not hold up, the award profiles above still offer a grounded set of lessons on managing existing-conditions risk and long-lead procurement.